Project Overview
NORTHSIDE GWINNETT HOSPITAL 3
We have been performing projects at Northside Gwinnet Hospital for the last few years, and they have been so pleased with our past work that they awarded us another million dollar contract.
This is the first phase of the work and consisted of milling down the existing pavement 1.5 inches, clean, apply liquid tack coat, then pave with 1.5 inches (compacted thickness) of 9.5 mm asphalt topping. All milling and cleaning was performed at night, and the project completed in 4 days. One very large parking lot was paved, as well as many of the drive lanes.